138kV Delivery Substation / Transmission Line

Shelby, Ohio
This project included coordination with AEP for 138kV interconnection, four 138kV circuit breakers, a 138kV circuit switcher, coordination of obtaining railroad occupancy agreements, three 15kV reclosers, associated protective relaying, five miles of 138kV transmission line with fiber optic static wire, relay settings and start-up assistance.
Owner
City of Shelby
Project Cost
$48 million
Completion Date
2008